The Board That Approved Everything and Decided Nothing
November 4, 2026
The Hotel Opening GM Isn’t the Operations GM
Opening the Hotel and Operating It Are Different Jobs
The grand opening of the beachfront resort in the Riviera Nayarit looked like a triumph. The property was full. The international press had arrived. The developer stood on the terrace with the Pre-Opening General Manager and raised a glass to what appeared to be a flawless execution.
The GM had earned the moment. Over the preceding months, he had absorbed the punishment of a difficult project — construction pressure, permitting friction, equipment stuck in customs, hundreds of hospitality staff recruited and trained from scratch. On opening day the property worked.
Eighteen months later, the mood had changed. The hotel was open, but the operation had not settled. Staff turnover in housekeeping and food service had climbed. Preventive maintenance was slipping. Budget variances stayed in the red. Corporate accounts were complaining about billing reconciliations that took weeks.
The developer, once the GM’s greatest champion, was exasperated. He had been brilliant during construction. What happened to him.
Nothing had happened to him. The executive had not changed. The track conditions had.
Hotel Opening GM: The lifecycle the title obscures
Hospitality developers often treat “General Manager” as a single job. It is not. A hotel moves through several distinct operating environments in its first several years, and the leadership mandate looks different inside each one.
Pre-opening is a critical-path exercise. It begins as much as two years before opening for a large complex property. The work is planning, budgets, procurement, systems setup, sales and marketing pipeline, hiring, and training — most of it while parts of the environment are still incomplete. The received idea that pre-opening rewards improvisation over structure is misleading. Good pre-opening leadership requires an unusual capacity to build systems inside ambiguity, not to bypass them.
Ramp-up begins the day the hotel opens and is often where the wheels come off. The building is finished, the plans meet real demand, and every workaround that got the property to opening day has to survive contact with paying guests. This phase can last many months.
Stabilization is when the operating model settles. Repeatable disciplines around labor, maintenance, revenue management, and department leadership take hold. Financial stabilization for a resort property can take three to four years, sometimes longer.
Mature operations is what most people picture when they say “running the hotel.” It is where asset economics compound or erode over years.
The problem the article’s opening scene describes is not a personality collapse. It is a leadership system built for phase one still running in phase three.
What actually breaks between opening and stabilization
The behaviors that get a property open are not inherently pathological. Some of them are necessary. The issue is what happens when they persist past the phase that required them.
Centralized decision-making. During pre-opening, decisions cluster near the GM because dependencies are tight and deadlines unforgiving. After opening, the GM has to progressively distribute that authority into department leadership. When they don’t, capable Food & Beverage directors and Executive Housekeepers begin to resign — not because the GM has become worse, but because the operating model that made sense in month minus four does not make sense in month fourteen.
Culture built on extraordinary effort. Opening teams often bond through intensity. The camaraderie is real, and it is useful during the sprint. It cannot become the permanent employment proposition. When the adrenaline fades and the daily rhythm takes over, employees who were motivated by the launch begin to experience the absence of structure as chaos. Retention deteriorates.
Workarounds that were never converted. The most durable damage from a difficult opening is often technical debt. Invoice coding shortcuts, vendor relationships that never got contracted, informal maintenance routines, staffing arrangements outside the formal roster, systems that half-work because someone patched around them at three in the morning. Every one of these was rational at the time. In year two they show up as audit findings, phantom inventory, cost of goods sold that no one can explain, and asset condition problems that were quietly deferred.
Somebody has to retire the debt. The most useful question about an opening GM is not whether they can survive stabilization. It is whether they can systematically undo the workarounds they themselves created.
The owner’s decision, and it is not binary
The received framing gives owners two options: keep the opening GM or replace them. There is a third that is often the right one.
The specialist path. Some GMs genuinely specialize in openings. Their strengths are mobilization, sequencing, and getting an asset across a finish line under compressed conditions. A developer who hires a specialist should say so explicitly, define the handoff criteria — critical systems stabilized, department heads operating independently, maintenance programs functioning, reporting reliable, turnover normalizing, commercial pipeline established — and plan the succession before the ribbon is cut, not after year two collapses.
The pace-shifter path. Some GMs can change operating mode as the asset changes. They can hold the intensity of pre-opening, then progressively delegate, systematize, and take a longer view. The right test is not whether they have opened five hotels in ten years — that pattern is a question, not a verdict. The test is whether they have demonstrated the transition before. Have they taken a property from opening through stabilization? Can they describe what changed in their own leadership between month three and month thirty?
The structural path. Sometimes the useful intervention has nothing to do with replacing the GM. It is separating the work that belongs to development from the work that belongs to hotel operations. Construction closeout, contractor management, FF&E procurement, permitting, and technical services often belong with a dedicated project manager or the operator’s technical services group — not with the person who is supposed to be building the commercial engine and training department heads. When a GM is buried in development friction that should have been carried elsewhere, they don’t collapse in year two because they lack systems capability. They collapse because they never had the room to build the operating team.
The owner’s real decision is not which GM archetype to hire. It is which of these three paths the asset actually needs.
What search committees should test for
If the mandate is to bridge opening through operations, credentials and opening pedigree are not enough. Three things are worth testing directly.
Pace-shifting evidence. Ask the candidate to describe how their leadership changed between opening and stabilization at a prior property. Listen for whether they can tell the story as a transition — specific delegations made, workarounds retired, disciplines installed — or whether they describe the same operating mode throughout. The candidate who cannot describe how they changed probably didn’t.
Systems fluency versus firefighting pride. Listen to how they narrate past successes. Do they celebrate the midnight crises they personally solved, or do they talk about how quickly they got their department heads to operate independently? The leader who loves being the irreplaceable hero will struggle when the operation requires them to become an empowering architect. The best sentence a candidate can offer about a past property is usually about the team that ran it after they left.
Operating economics across phases. Ask how the property’s economics changed from opening through ramp-up and what disciplines they installed as occupancy normalized. A candidate who can only speak in opening-day metrics — ADR, launch press, initial NPS — is different from one who can discuss what happened to labor cost per occupied room, GOP flow-through, and retention as the property matured. Both may be excellent hoteliers. They are calibrated for different phases.
Honor the builder, protect the asset
Getting a resort from bare earth to a functioning hotel is a genuine feat. The leaders who can do it possess rare gifts, and they deserve the recognition they earn on opening night. But building an asset and shepherding an investment are not the same assignment. The developer who understands this early makes better decisions about leadership sequencing, about which work belongs to development versus operations, and about what the specific GM in front of them can actually carry across the phases still ahead.
Opening day does not end the leadership transition. It begins the next one.
Charlie Solorzano is Managing Partner at Alder Koten, working with hospitality organizations on C-suite and senior leadership searches across the U.S. and Mexico. His hospitality executive search work spans hotels, resorts and tourism, with an emphasis on matching leadership capability to the operating environment, guest proposition, ownership context and strategic mandate.
Is Your GM Built for the Phase Your Asset Is Actually In?
Opening a hotel and operating one are different jobs, and not every GM makes that transition. Let’s talk about which path your asset actually needs.
Schedule a Confidential ConsultationWhy does a GM who nailed a hotel’s opening sometimes struggle a year or two later?
Because opening and operating are different phases with different requirements. Centralized decision-making, extraordinary-effort culture, and improvised workarounds are often necessary during pre-opening, but the same behaviors create department-head attrition, retention problems, and unexplained cost issues once the property moves into stabilization.
What are the distinct phases a hotel moves through after construction?
Pre-opening, which is a critical-path planning and systems-building exercise; ramp-up, which begins the day the hotel opens and is where improvised workarounds meet real guest demand; stabilization, when repeatable disciplines take hold, often over three to four years; and mature operations, where asset economics compound or erode over the long term.
What technical debt does a difficult hotel opening typically leave behind?
Invoice coding shortcuts, uncontracted vendor relationships, informal maintenance routines, staffing arrangements outside the formal roster, and systems patched together under deadline pressure. Each was reasonable in the moment; in year two they surface as audit findings, unexplained cost of goods sold, and deferred asset condition problems.
What are an owner’s options if the opening GM isn’t suited to running the stabilized property?
Three paths beyond simply keeping or replacing them: hiring a specialist explicitly for openings and planning the handoff in advance, finding a “pace-shifter” who has demonstrably taken a property through the full transition before, or restructuring the role so development-related work like construction closeout and FF&E procurement sits outside the GM’s mandate entirely.
What should a search process test for when hiring a GM meant to bridge opening through stabilization?
Whether the candidate can describe specific delegations and workarounds they retired as the property matured, whether they narrate past success through team independence rather than personal firefighting, and whether they can discuss operating economics like labor cost per occupied room and GOP flow-through, not just opening-day metrics.